PolyHorse with PowerAssist helps contractor tackle
cross-country fusions
Many people have heard of a
cross-country foot race. A crosscountry
race is a timed event where
competitors face different challenges
over a fixed distance. The
obstacles can range from weather to
adverse terrain. The thrill of the race
might be the obstacles awaiting the
competitors at every turn. However,
no one would blame a competitor
for using a shortcut in the race, if it
were legal and within the rules.

Near Loudonville, Ohio, R&R
Pipeline just finished a cross-country race of sorts. They were one of two contractors used to fuse a
great distance of pipe in less than two months. Under a time limit and with several obstacles, R&R
turned to some productivity shortcuts to gain speed and efficiency in efforts to meet the deadline.
The first stage of the race was a one-week time period to get the bid drawn up. R&R was
awarded the contract by Dominion East Ohio to install 38,000 feet of high density polyethylene
pipe (HPDE) on April 2nd. Four days later, the first six trucks delivered pipe. The finish line for the
project was a very speedy May 31st.
The cross-country metaphor extends even further. R&R Pipeline was forced to perform some
of the fusions and directional bores far away from the roads. The boring of holes across fields and
pastures was required by the Environmental Protection Agency (EPA). The measure was in place
to protect cornfields that could hold artifacts from the Mohican Indians, as well as other Native
American tribes.
With 30,000 feet of 12-inch and 8,000 feet of 8-inch pipe to install, R&R Vice President Jeff
Emery began mobilizing resources, which included 50 fusion operators in the 140 person firm,
immediately after winning the bid.
Along with the miles of pipeline to
be fused, 29 tie-ins and tapping tees
were required.

The rural hills created a few
hurdles, leaving spotty to non-existent
cell phone reception to communicate
between the 38 R&R workers
on site. Multiple job sites operated
in unison, but at distances just out
of walkie-talkie range. Also, treecovered
hillsides offered little in
terms of right-of-ways. Mixed with the EPA concerns and outright speed
required to complete the job on time,
Emery and R&R turned to Morain
Sales and Service for answers or
shortcuts that could boost productivity,
while still doing great work for
Dominion East Ohio.
Jeff Hattendorf at Morain had
a few aces up his sleeve, including
one of the first McElroy PolyHorse
PowerAssist units ever put into the
field. The PowerAssist is a hydraulically
powered roller that replaces the
pivoting roller on the original PolyHorse design. The PolyHorse is a pipe-handling system for 3” to
20” pipe (90mm to 500mm) that allows the pipe to be delivered and stored at a single location. The
powered roller aids in maneuvering sticks of pipe up, down and into the fusion machine.

With the PolyHorse PowerAssist and a TracStar 412, R&R’s fusion operators averaged 29 joints
of 12-inch pipe per work day. However, the productivity didn’t stop there. When fusing some of
the longer lengths of pipe out of the 38,000 total feet of pipe, R&R used a technique called piggybacking.
Piggybacking is the practice of having two machines staged at one location so that a
fusion technician can fuse one joint while another cools. Once a joint is cooled and pulled out of the
machine, the process starts over and rotates from machine to machine, using the downtime of the
cooling period to the operator’s advantage.
Emery’s go-to fusion machine of choice on this job was the TracStar 412. Between the four 412
machines on site, Emery found the maneuverability and power of the TracStar to his liking.
“I wouldn’t buy a wheeled machine. The TracStar just has too many benefits,” said Emery.
“McElroy’s tracked machines are easier to line up and move.”
R&R also found value in a simple, but often overlooked piece of the McElroy productivity tool
lineup. On the opposite end of the fusion site from the PolyHorse, R&R used pipe stands to save
wear and tear on the TracStar, keeping the length of pipe close to parallel for faster facing and hi/
low adjustment, and for ease in pulling the length of pipe after a completed joint.
When all was said and done, R&R completed the job a week and a half early. The productivity
of all the tools, finding a job site setup that works and working hand-in-hand with a local McElroy
distributor proved highly productive in the long run.
Contact Information:
McElroy PR and Marketing Department
Tyler Henning, public relations specialist
Phone: (918) 831-9286
E-mail: thenning@mcelroy.com
|